Update – 09/16/2020

Work on the project was slowed for several weeks as we waited for ComEd to relocate their underground facilities out of conflict with the noise wall south of Bristol Trail Road. The facility was moved just before the Labor Day holiday. We were able to find a rain-free window last week to jog southbound Quentin Road traffic east so work on the wall could begin. Crews will begin drilling the foundations this week and anticipate installing the columns and panels next week. The adjacent sidewalk, topsoil and landscaping work will be scheduled after the wall is compete. This work will take several weeks to complete and after which southbound traffic will be returned to the outermost lane. After traffic is returned to the outermost lanes, the final asphalt surface will be placed. We are currently anticipating this work to begin in mid-October. This will be followed by placement of the permanent pavement markings, final landscaping and turning on the new traffic signals. Other work that is anticipated is a structural concrete liner that will be placed in an existing culvert that crosses under Quentin Road, north of East Cuba Road. Decorative landscaping stone is being installed between the noise abatement Read More

Update – 08/17/2020

Over the last couple of weeks, permanent traffic signal equipment was installed. In addition, concrete sidewalk placement on the west side of Quentin Road continued and is nearly complete. After traffic was moved to the outside drive lanes on Wednesday, July 29th, work in the medians was allowed to move forward. This included removing the temporary staging pavement and placing concrete curb and gutters.     Topsoil was respread on the west side of Quentin Road and in the medians. The topsoil was tilled, fine graded and the permanent seed with erosion control blanket was placed. Sod will be placed in the areas between the curb and sidewalk at a future date, as will trees in the parkway and medians. Asphalt placement in the turn lanes is scheduled for this week. Delays continue due to underground power lines in conflict with the final remaining portion of noise wall south of Bristol Trail Road. After the lines are moved, southbound traffic will once again need to be jogged to the east for the section north and south of Bristol Trail Road so the wall can be built. This temporary traffic change will be in place for about a month. Upon completion Read More

Update – 07/27/2020

Concrete sidewalk placement on the west side of Quentin Road started this past week. The sidewalk will extend from just north of Pine Lake Circle to just south of Illinois Route 22. The sidewalk is placed on a 4” aggregate base. Placement of the sidewalk is anticipated to continue through the end of the week.   Noise abatement wall construction continued last week.  Crews installed columns, panels, and decorative caps at multiple locations and power washed the walls.  The noise walls are near complete with the exception of a section south of Bristol Trail Road.  This location will be built once the utility company relocates the power lines in conflict.   Other project work over the last couple of weeks included completion of the retaining wall north of Lea Lane and installation of traffic signal wiring.  Work anticipated over the next couple of weeks includes installation of the new traffic signal posts and mast arms.  Traffic will be placed into a new traffic pattern on Wednesday, July 29th.  The northbound and southbound lanes will be jogged to the outside lane of the new roadway.  This will allow for the removal of temporary pavement and placement of median curb and permanent pavement.  Read More

Update – 07/15/2020

Construction started on a retaining wall north of Lea Lane.  A truck was supplied by ComEd to support a utility pole while the wall is being constructed due to excavations near the base of the pole.  Construction of this wall is anticipated to be complete this week.   Hot-mix asphalt was placed on the north half of West Cuba Road and at Pheasant Ridge Drive.   Paving is completed for this stage of work.  The next area of permanent pavement will be in the medians.   Noise abatement wall panel installation as well as drilling and pouring foundations for the noise abatement walls resumed over the last two weeks.  Columns were placed on the poured foundations.  Additional noise abatement wall panels are expected to be installed this week.  One column north of Pheasant Ridge Drive and several columns south of Bristol Trail Road will be completed at a later date due to utility conflicts.   Other project work over the last couple of weeks included installing traffic signal foundations at the West Cuba Road and East Cuba Road intersections.  Work anticipated over the next couple of weeks includes grading for sidewalk on the west side of Quentin Road and pulling traffic Read More

Update – 06/30/2020

Hot-mix asphalt paving operations took place over the last two weeks. Crews placed three of the four lifts on future southbound Quentin Road and West Cuba Road. The final surface lift will be placed near the end of the project.   Between the top two lifts of hot-mix asphalt, a joint sealant was placed. The sealant prevents water infiltration which leads to premature joint failure during freeze-thaw cycles. The joint sealant placement is tested to assure the proper application rate.   Work on West Cuba Road proceeded quickly as the southern and center sections were constructed. This required multiple traffic pattern changes. Work is ongoing on the northern portion of West Cuba Road.   Other project work over the last couple of weeks included installation of conduit for traffic signals and installation of railings on retaining wall parapets. Work anticipated over the next couple of weeks includes construction of a retaining wall north of Lea Lane, resuming work on select portions of the noise abatement walls, and sidewalk placement. Please check the Photos tab for more in-depth information regarding the project.

Update – 06/16/2020

Over the last two weeks crews installed concrete curb and gutter throughout the project, including portions of the future median areas.   Work on extending the existing culvert south of Illinois Route 22 was also completed. Crews placed reinforcing steel and cast the concrete in place. The extension is to accommodate a new sidewalk which will be placed at a later date.   Noise abatement wall panels were placed at a number of project locations. Foundation drilling, along with concrete placement and installation of the remaining portions of the wall will resume when crews and equipment become available.   Other project work over the last couple of weeks included roadway excavation, grading, and aggregate placement for the balance of the future southbound Quentin Road.  Asphalt placement will begin this week and will continue through next week.  Please watch for trucks leaving and entering the road.  Also anticipated this week, eastbound traffic on West Cuba Road will be jogged to the south so crews can construct the middle portion of the road. Please check the Photos tab for more in-depth information regarding the project.

Update – 06/02/2020

Crews completed underground storm sewers for roadway construction last week on both Quentin Road and West Cuba Road.  Two culvert pipes and an extension of an existing box culvert, all immediately south of Illinois Route 22, are the last of the drainage work remaining until the final stages of the project.   Roadway excavation, grading, and aggregate placement were completed from Pine Lake Circle to Pheasant Ridge Road.  This work will continue northward to Bristol Trail Road over the next week.   Other project work over the last couple of weeks included placement of curb and gutter, which comprised areas of the new landscaped median north and south of Lea Lane. Crews also continued staining retaining wall parapets at the south job limits. Asphalt for the new roadway is anticipated for the week of June 8th. Please watch for trucks entering and leaving the road. Work on noise walls and retaining walls between Pheasant Ridge Road and Lea Lane may resume the week of June 8th as we are anticipating some of the utility conflicts to be moved this week.   Please check the Photos tab for more in-depth information regarding the project.

Update – 05/18/2020

Work on the noise abatement walls is ongoing. Portions of precast columns and panels have been installed between Pheasant Ridge Drive and Buffalo Creek. Certain post and panel locations will be installed at a later date as we continue to work through underground conflicts. At this time there is not a date when each conflict will be resolved but continue to work and meet with utility companies to work through these issues.   Aggregate for the new roadway has been placed at the northern and southern project limits. This work will continue through the central portion over the next several weeks as weather and ground conditions allow.   Concrete curb and gutter placement started last Friday (5/15/2020). A machine is used to “slip form” the majority of the curb to eliminate the need to use wood forms and shaping by hand. This work will continue intermittently over the next several weeks and will include segments of the new raised median curb.   Over the last couple of weeks other project work included storm sewer structure and pipe installations. Storm sewer installation is expected to be complete this week, pending weather and ground conditions. Crews also started work to extend an Read More

Update – 05/04/2020

Old Quentin Road pavement removal is compete.  This will allow storm sewer crews to install the remaining pipe crossings.  Storm sewer work is anticipated to continue for the next couple of weeks. Work on noise abatement walls is ongoing.  Portions of precast columns and panels have been installed at Pheasant Ridge Drive and Buffalo Creek.  More noise wall columns and panels in this area are expected to be installed this week.  There are a few post and panel locations which will be installed at a later date as we work through underground conflicts. Work continues on the retaining wall at Buffalo Creek.  Reinforcing steel is anticipated to be installed on top of a portion of the wall this week and will be followed by concrete.  The noise wall will be extended on top of the retaining wall.   Seeding on the east side of Quentin Road is nearly complete.  The remaining areas on the east side of Quentin Road which have not been blanked will be seeded with a native grass seed mixture when planting time and temperatures are appropriate.   Other project work over the last couple of weeks included subbase excavation and preparation for the roadway aggregate north Read More

Update – 04/21/2020

Noise abatement wall construction continues.  The remaining precast columns and panels have been installed between West Cuba Road and Pheasant Ridge Drive.  Noise abatement wall column installation will begin this week north of Pheasant Ridge Drive.   Work continues at multiple retaining walls throughout the project limits.  The parapet for the wall north of Pine Lake Circle is now complete since the last portion was poured on Friday, April 17th.  Work on the retaining wall north of East Cuba Road is ongoing and is expected to continue for the next several weeks.   Permanent landscaping on the east side of Quentin Road continues.  Sod is being placed between the curb and shared use path.  West of the shared use path, crews will place seed and erosion control blanket.  Landscaping on the east side of Quentin Road will be complete near the end of this week.   Other project work over the last couple of weeks includes removal of the old southbound Quentin Road lanes and portions of West Cuba Road.  Crews will removed existing storm sewer, curb and gutter and driveways within the project limits.  In the next couple of weeks, installation of storm sewer and placement of aggregate for Read More