Update – 5/21/2019

Last week storm sewer installation continued as the crew started working on its second system of pipes.  The storm sewer crossing under Quentin Road between Bristol Trail and Lea Lane/Greenwood Drive was completed on Saturday when traffic was much lighter which helped minimize traffic impacts during the work week.  We will provide notification when the next crossing requiring lane closures is expected.  Crews also started placing roadway embankment at multiple locations throughout the project limits.  Sheet pile installation north of Greenwood Drive is complete and removal of poor soils has started.  As these soils are removed a two foot layer of aggregate will be placed and roadway embankment will be installed.  This week roadway embankment and installing storm sewer pipes will continue. Work on a retaining wall south of Illinois Route 22 will begin this week and continue over the next month.  Installation of a second temporary sheet pile wall south of Bristol Trail will begin near the end of this week. Nicor Gas paved Boschome Drive and reopened the road to traffic on Friday, May 17th.  They will be working on restoration landscaping in the upcoming week as site conditions allow.  AT&T crews will continue removing retired cables and Read More

Update – 5/13/2019

Once again, rain limited construction activities last week.  Storm sewer installation started north of East Cuba Road and will continue through the middle of the week.  Installation of the next system of pipes will begin near the end of the week.  This system will require installing a pipe crossing under Quentin Road between Bristol Trail and Lea Lane/Greenwood Drive.  Because of this, Quentin Road may be reduced to one lane during off-peak hours which could cause traffic delays.  Sheet pile installation north of Greenwood Drive is nearly complete. Once finished, it is anticipated the sheet pile crew will move to a location south of Bristol Trail to begin installation on a second temporary soil retention wall.  Weather permitting; roadway embankment placement is also scheduled this week. Nicor Gas completed the retirement of the old 18” transmission line last week.  They will be restoring the excavation and repaving Boschome Drive at Quentin Road.  The closure is expected to remain in place until May 17th.  More information regarding the closure can be found by clicking here. AT&T crews will continue removing retired cables and poles that interfere with the improvement over the next couple of weeks. Please check the Photos tab for Read More

Update – 5/6/2019

Rain limited construction activities on the project most of last week.  Sheet pile was able to be installed north of Greenwood Drive on Thursday and Friday.  Installation is expected to continue through the end of this week.  Also planned for this week is roadway embankment placement and storm sewer installation as weather and site conditions allow.   Since relocation of the majority of utility conflicts iscomplete, an updated project schedule has been posted to the project website.  The update can be viewed by clicking here.   Nicor Gas is scheduled to retire the old 18” transmission line this week.  When complete, Boschome Drive at Quentin Road will be restored. The detour is expected to remain in place until May 17th.  More information regarding the closure can be found by clicking here. AT&T crews will continue removing retired cables and poles that interfere with the improvement over the next couple of weeks. Please check the Photos tab for more in-depth information regarding the project.

Update – 4/30/2019

Aggregate was placed in both ground improvement areas between East and West Cuba Roads.  This final lift of aggregate will transfer the load of the roadway embankment onto the underground concrete columns to bridge over the poor subsurface soils.  Topsoil was also stripped at several locations within the project limits.  The topsoil will be respread when embankment and roadway construction is complete.  This coming week, roadway embankment placement and storm sewer installation is anticipated to begin.  Additionally, installation of the second line of sheet piles north of Greenwood Drive is expected to resume.  We are hoping for a more favorable forecast as much of this work is weather dependent.   Nicor Gas is scheduled to retire the old 18” transmission line early next week.  When complete, Boschome Drive at Quentin Road will be restored.  The detour is expected to remain in place until May 17th.  More information regarding the closure can be found by clicking here. AT&T crews will continue removing retired cables and poles that interfere with the improvement over the next couple of weeks. Please check the Photos tab for more in-depth information regarding the project.

Update – 4/23/2019

Installation of the underground concrete columns was completed last week in the ground improvement areas between East and West Cuba Roads.  Testing was performed on the columns by applying a vertical load to assure they meet required bearing pressures.  Metal sheet piles were installed along the eastern right of way north of Greenwood Drive.  A second line of sheets will be installed later this week approximately 45 feet west after portions of the existing pavement are removed.  The sheets will act as a temporary retaining wall.  Soft, poor soils between the sheet walls will be removed and replaced by materials suitable for roadway construction.  Later this week, earth excavation and storm sewer installation operations will begin.   Nicor Gas crews completed the preparatory work necessary to retire the old 18” transmission line.  Due to unforeseen circumstances, however, Nicor has changed the retirement date to the first week of May.  Because of this, Boschome Drive at Quentin Road will remain closed until May 17th.  More information regarding the closure can be found by clicking here. AT&T crews completed splicing in the new cables this past weekend.  The old cables and poles that interfere with the improvement are scheduled to be removed Read More

Update – 4/15/19

Work continued on the new retaining wall south of Boschome Drive this past week.  Concrete in the final section of wall is anticipated to be poured Monday, April 15th.  Installation of the subsurface concrete columns in the ground improvement areas between East and West Cuba Roads started this past week.  Despite being hampered by the rain and snow, the columns are expected to be complete this week.  Equipment is being mobilized to begin the installation of sheet piles north of Greenwood Drive.  The sheet piles will take approximately two weeks to install.  Work upcoming in the next couple of weeks includes storm sewer installation and earth excavation operations.  Please continue to be aware of workers when driving through the work zone.  Nicor Gas completed connections and other ancillary work necessary for to retire the old 18” transmission line last week.  The final connections and retirement is expected to be complete Wednesday, April 17th.   During the second half of this week, Nicor Gas will begin restoring disturbed areas and removing equipment from the site.  Boschome Drive at Quentin Road will remain closed and Nicor Gas is expecting to have it reopened by April 30th.  More information regarding the closure can be Read More

Update – 4/8/19

Reinforcing steel was placed at the new retaining wall south of Boschome Drive this past week and the first section was poured on Friday.  When complete, the wall will have a stained surface which will simulate a stacked stone.  A section of wall is scheduled to be poured each day this week and into the beginning of next week.  Installation of the subsurface concrete columns in the ground improvement areas between East and West Cuba Roads is expected to begin on Tuesday, April 9th.  This operation is expected to continue through the end of next week.  When the concrete columns are complete, they will be loaded with roadway embankment and monitored for settlement.  Installation of sheet piles north of Greenwood Drive is scheduled to begin later this week.  The sheet piles are being installed to assist in removal of poor subsurface soils in the area.  As construction activities continue to pick up throughout the construction site, please continue to watch for workers as well as trucks entering and leaving the roadway.  Nicor Gas crews tied in the new 4” distribution system in the area of Lea Lane, Greenwood Drive and Bristol Trail this past week.  Backfilling and restoration work at Read More

Update – 4/1/19

Preparation work for the two ground improvement areas on the east side of Quentin Road between East and West Cuba Roads was completed this past week.  Installation of the subsurface concrete columns in these areas is expected to begin next week.  Stud shears were welded onto the H-piles installed for the retaining wall south of Boschome Drive which will hold the concrete to the H-piles.  This week, reinforcing steel will be placed and concrete will be poured for this wall.  Installation of sheet piles north of Greenwood Drive is scheduled to begin later this week.  This operation will take approximately two weeks to finish.  The sheet piles are being installed to assist in removal of poor subsurface soils in the area. Nicor Gas crews continued work on the 4” distribution system in the area of Lea Lane, Greenwood Drive and Bristol Trail.  The installation of the 4” pipes in this area is complete.  Nicor is expecting to bring these pipes into service by April 12th.  Nicor Gas closed Boschome Drive this morning to make the final connection of the 20” steel high pressure line.  The road is expected to be closed until April 30th.  Please follow the posted detour.  More Read More

Update – 3/26/19

Work continued preparing the two ground improvement areas on the east side of Quentin Road between East and West Cuba Roads.  Soils in these areas were removed and replaced by aggregate which will act as a working platform for the equipment needed to install subsurface concrete columns. Installation of the aggregate will be completed by the end of the week followed by the concrete columns next week.  The temporary pipes installed over the last week and a half were tied into existing pipes to bypass the sanitary line in this ground improvement area.  Steel H-piles were installed for a retaining wall south of Boschome Drive.  Over the next two weeks, it is anticipated reinforcing steel will be placed and concrete will be poured for this wall.  Sheet piles north of Greenwood Drive are scheduled to be installed beginning this week.  This operation will take approximately two weeks to finish.  The sheet piles are being installed to assist in removal of poor subsurface soils in the area. AT&T crews continue pulling new cables in conduits and splicing aerial cables at various locations throughout the project.  Splicing on both the fiber optic and copper cables is expected to be complete in April.  The Read More

Update – 4/23/2019 – Boschome Drive Detour

Boschome Drive will be closed to traffic from Quentin Road to South Boschome Circle. This closure will be in place from April 1st to May 16th to allow Nicor Gas crews to connect the new 20” steel pipe to the existing 18” pipe under the roadway. During the closure, local traffic will be able to access Boschome Road from the east only. The detour mapped below will be posted. The detour mapped below will be posted.