Update – 3/18/2019

Work continued preparing the two ground improvement areas on the east side of Quentin Road between East and West Cuba Roads.  Temporary pipe will be installed this week to bypass the existing sanitary sewer around the ground improvement areas.  Steel H-piles will be installed this week as construction begins on a retaining wall south of Boschome Drive.  Sheet piles will also be installed for a temporary soil retention system north of Greenwood Drive. Nicor Gas crews continued work on the 4” distribution system in the area of Lea Lane, Greenwood Drive and Bristol Trail.  Work on the distribution system is anticipated to be complete the week of March 25th.    AT&T crews continue pulling new cables in conduits and splicing aerial cables at various locations throughout the project.  Splicing on both the fiber optic and copper cables is expected to be complete in April.  The old cables are scheduled to be taken out of service April 18th through April 22nd.  Please check the Photos tab for more in-depth information regarding the project.

Update – 3/12/2019

The contractor continued preparation work on two ground improvement areas on the east side of Quentin Road between East and West Cuba Roads.  This week excavation work to install a temporary sanitary sewer bypass system around the ground improvement areas will begin. Temporary concrete barrier walls were installed on the project site this past week.  Work will continue this week drilling and pinning these walls to the existing pavement. Nicor Gas crews continued installing new valves at Boschome Drive and Quentin Road, along with a series of valves across from Bristol Trail.  This week Nicor crews plan to install the 4” distribution system in the area of Lea Lane, Greenwood Drive and Bristol Trail.  This work is anticipated to be complete the week of March 25. AT&T crews continue pulling new cables in conduits and splicing aerial cables at various locations throughout the project.  Splicing on both the fiber optic and copper cables is expected to be complete in April.  The old cables are scheduled to be taken out of service April 18th through April 22nd. Please check the Photos tab for more in-depth information regarding the project.

Update – 3/4/2019

The project contractor started preparation work on two ground improvement areas on the east side of Quentin Road between East and West Cuba Roads.  These improvement areas were identified during the design phase as having substandard soils.  Once the substandard soils are removed, a working platform on concrete piles will be constructed before placement of roadway widening embankment.  This week the contractor is anticipating installing temporary concrete barrier walls at several various locations within the project limits. AT&T crews continue pulling new cables in conduits and splicing aerial cables at various locations throughout the project.  In addition, work has started on the installation of controller cabinets.  Splicing on the fiber optic cables is expected to be complete in April at which point the old fiber will be taken out of service.  This work is scheduled to take place April 18th through April 22nd.  Installation and splicing on the copper cables will continue through the end of March.  Once complete, the copper lines in conflict can start to be retired. Nicor Gas crews completed installing 20 inch steel pipe by open cut south of West Cuba Road.  The new 20 inch pipeline from Illinois Route 22 to Bristol Trail was “livened” Read More

Update – 2/20/2019

Nicor Gas crews continue to install 20 inch steel pipe by open cut south of West Cuba Road.  This work is anticipated to be complete at end of February.  The new 20 inch pipeline from Illinois Route 22 to Bristol Trail is scheduled to be “livened” on Friday, February 22.  Following the livening of the 20 inch pipe, a series of valves and smaller pipes need to be installed north and south of Bristol Trail.   This work will continue through March.  AT&T crews are completing installation of underground conduit.  They will continue pulling new cables in the conduits and splicing aerial cables at various locations throughout the project.  Cable installation and splicing on the main transmission line is anticipated to be complete at the end of March.  Once this is complete, work will begin to transfer to communications from the transmission line to smaller distributor cables.  Lines in conflict can start to be retired. While the utilities have made steady progress, conflicts with the roadway improvement continue to exist preventing significant work from moving forward.  While we continue to assess the extent of utility delay impacts, it is evident some work items will not be completed until the 2020 construction Read More

Update – 1/21/2019

This past week, gas pipe installation resumed.  Nicor contractors installed 20” pipe by traditional open cut methods.  AT&T crews continue installing underground ducts throughout the project limits.  AT&T crews also prepared for concrete pads which will be installed to accept new controller cabinets.  Comcast Cable crews relocated underground cabling in conflict with the proposed improvements. Please check the Photos tab for more in-depth information regarding the project.

Update – 1/14/2019

This past week areas of Quentin Road were milled and repaved due to the poor condition of the pavement. These areas were overlayed with new hot mix asphalt. Your patience during this emergency operation is appreciated. Utility companies continued moving facilities in conflict with the proposed improvements. AT&T crews continue installing underground ducts throughout the project limits. Please check the Photos tab for more in-depth information regarding the project.

Update – 1/7/2019

During the week of December 17th, existing pavement markings were removed and new markings were installed. Traffic was then switched onto the temporary pavement with a new lane configuration. Please be alert of the lane changes when driving through the construction zone. Utility companies continued moving facilities in conflict with the proposed improvements. Nicor Gas continued welding and installing steel pipe sections on the east side of Quentin Road both north and south of East Cuba Road. The long line of assembled 20” steel pipe on the east side of the road was pulled in place by the boring machine near Boschome Drive. AT&T crews continue installing underground ducts north of West Cuba Road and north of Lea Lane. Please check the Photos tab for more in-depth information regarding the project.

Update – 12/17/2018

Preparations have started for shifting Quentin Road traffic onto temporary pavement. Traffic workers installed vertical panels along what will be the new right edge line for southbound Quentin Road. Workers also started removing the existing pavement markings which will be replaced with temporary markings to accommodate the shifted lanes. The complete traffic switch will be finished this week. Please be alert of the lane changes when driving through the construction zone. Utility companies continued moving facilities in conflict with the proposed improvements. Nicor Gas continued welding and installing steel pipe sections on the east side of Quentin Road both north and south of East Cuba Road. The long line of assembled 20” steel pipe on the east side of the road is scheduled to be pulled in place this week by using a boring machine near Boschome Drive. Nicor also continued work on the smaller 4” distribution line north of Pheasant Ridge Road. AT&T crews continued installing underground ducts north of West Cuba Road and north of Lea Lane. Please check the Photos tab for more in-depth information regarding the project.    

Update – 12/10/2018

Work continued this week on grading aggregate shoulders and ditches along the west edge of the new temporary pavement. Traffic is anticipated to be shifted west soon so that work can begin on the east side of the road. Please continue to be diligent watching for workers throughout the construction zone. Utility companies continued moving facilities in conflict with the proposed improvements. Nicor Gas crews welded and installed steel pipe sections on the east side of Quentin Road both north and south of East Cuba Road. Nicor also installed new service connections to individual residences from relocated gas lines. AT&T continued installing underground ducts near Pine Lake Circle and West Cuba Road. Please check the Photos tab for more in-depth information regarding the project.