Nicor Gas continues welding and assembling the new 20 inch steel pipe which will replace an 18 inch line. Portions of this pipe just south of Illinois Route 22 have been “pulled” into place. The work effort to relocate this line will continue southward. AT&T continued hanging new aerial cable at the southern job limits and installing underground ducts on the northern job limits. Comcast Cable started installing underground conduits crossing Quentin Road.