Update – 10/15/2018

Nicor Gas continues welding and assembling the new 20 inch steel pipe which will replace the 18 inch line. The welded gas pipe staged on the east side of Quentin Road between East Cuba Road and Greenwood Drive will be pulled into place this week. South of East Cuba Road, gas company contractors continue excavating sending and receiving boring pits. Work on the four inch diameter distribution gas line continued this past week on the west side of Quentin Road around to and on the south of West Cuba Road. AT&T continued hanging new aerial cable and installing underground ducts throughout the job limits.

Please check the Photos tab for more in-depth information regarding the project.