Nicor Gas continued welding and assembling the new 20 inch steel pipe which will replace the 18 inch line. The welded gas pipe on the east side of Quentin Road between East Cuba Road and Greenwood Drive was pulled into place on Thursday, October 18th. South of East Cuba Road, gas company contractors continue excavating sending and receiving boring pits. Work on the four inch diameter distribution gas line continued this past week on the south side of West Cuba Road. AT&T continued hanging new aerial cable and installing underground ducts throughout the job limits.