Update – 11/12/2018

This week the roadway contractor started work necessary to construct the temporary pavement. Work included earth excavation, removal of curb and gutter, guardrail, and aggregate shoulders. The temporary pavement is needed to shift traffic on Quentin Road to the west in order construct the east side of the road. Utility companies continued moving facilities in conflict with the proposed improvements. Nicor Gas crews continued welding steel pipe sections and installing them on the east side of Quentin Road near the intersections of East Cuba Road and West Cuba Road. AT&T continued installing underground ducts and manholes throughout the project limits.

Please check the Photos tab for more in-depth information regarding the project.