Update – 11/19/2018

The roadway contractor continued work necessary to construct the temporary pavement this week. Pavement is anticipated to be placed in the upcoming days which will require lane closures at various times throughout the work day.  Delays should be expected.  The road will be widened to the west so that traffic can be shifted to construct the east side of the road.  Utility companies continued moving facilities.  Nicor crews continued welding steel pipe and pulling sections under East Cuba Road.  AT&T continued installing underground ducts and manholes throughout the project limits.

Please check the Photos tab for more in-depth information regarding the project.