Update – 12/03/2018

Despite the snow this past week, work continued on the temporary pavement after the snow was cleared. The final lift of hot-mix asphalt was placed Thursday which was followed by placement of an aggregate shoulder on its west edge. Traffic is anticipated to be shifted west soon so that work can begin on the east side of the road. Please continue to be diligent watching for workers throughout the construction zone. Utility companies, also hindered by the snow, continued moving facilities in conflict with the proposed improvements. Nicor Gas crews continued welding and installing steel pipe sections on the east side of Quentin Road. AT&T continued installing underground ducts near Pine Lake Circle.

Please check the Photos tab for more in-depth information regarding the project.