Update – 12/10/2018

Work continued this week on grading aggregate shoulders and ditches along the west edge of the new temporary pavement. Traffic is anticipated to be shifted west soon so that work can begin on the east side of the road. Please continue to be diligent watching for workers throughout the construction zone. Utility companies continued moving facilities in conflict with the proposed improvements. Nicor Gas crews welded and installed steel pipe sections on the east side of Quentin Road both north and south of East Cuba Road. Nicor also installed new service connections to individual residences from relocated gas lines. AT&T continued installing underground ducts near Pine Lake Circle and West Cuba Road.

Please check the Photos tab for more in-depth information regarding the project.