Update – 1/7/2019

During the week of December 17th, existing pavement markings were removed and new markings were installed. Traffic was then switched onto the temporary pavement with a new lane configuration. Please be alert of the lane changes when driving through the construction zone. Utility companies continued moving facilities in conflict with the proposed improvements. Nicor Gas continued welding and installing steel pipe sections on the east side of Quentin Road both north and south of East Cuba Road. The long line of assembled 20” steel pipe on the east side of the road was pulled in place by the boring machine near Boschome Drive. AT&T crews continue installing underground ducts north of West Cuba Road and north of Lea Lane.