Update – 1/14/2019

This past week areas of Quentin Road were milled and repaved due to the poor condition of the pavement. These areas were overlayed with new hot mix asphalt. Your patience during this emergency operation is appreciated. Utility companies continued moving facilities in conflict with the proposed improvements. AT&T crews continue installing underground ducts throughout the project limits. Please check the Photos tab for more in-depth information regarding the project.