Update – 5/6/2019

Rain limited construction activities on the project most of last week.  Sheet pile was able to be installed north of Greenwood Drive on Thursday and Friday.  Installation is expected to continue through the end of this week.  Also planned for this week is roadway embankment placement and storm sewer installation as weather and site conditions allow.   Since relocation of the majority of utility conflicts iscomplete, an updated project schedule has been posted to the project website.  The update can be viewed by clicking here.  

Nicor Gas is scheduled to retire the old 18” transmission line this week.  When complete, Boschome Drive at Quentin Road will be restored. The detour is expected to remain in place until May 17th.  More information regarding the closure can be found by clicking here.

AT&T crews will continue removing retired cables and poles that interfere with the improvement over the next couple of weeks.

Please check the Photos tab for more in-depth information regarding the project.