Update – 5/13/2019

Once again, rain limited construction activities last week.  Storm sewer installation started north of East Cuba Road and will continue through the middle of the week.  Installation of the next system of pipes will begin near the end of the week.  This system will require installing a pipe crossing under Quentin Road between Bristol Trail and Lea Lane/Greenwood Drive.  Because of this, Quentin Road may be reduced to one lane during off-peak hours which could cause traffic delays.  Sheet pile installation north of Greenwood Drive is nearly complete. Once finished, it is anticipated the sheet pile crew will move to a location south of Bristol Trail to begin installation on a second temporary soil retention wall.  Weather permitting; roadway embankment placement is also scheduled this week.

Nicor Gas completed the retirement of the old 18” transmission line last week.  They will be restoring the excavation and repaving Boschome Drive at Quentin Road.  The closure is expected to remain in place until May 17th.  More information regarding the closure can be found by clicking here.

AT&T crews will continue removing retired cables and poles that interfere with the improvement over the next couple of weeks.

Please check the Photos tab for more in-depth information regarding the project.