Update – 6/18/19

This past week earth excavation and roadway embankment placement continued.  The embankment placement included filling the deep excavations at the ground improvement areas between East and West Cuba Roads and north of Greenwood Drive.  Work this past week also included the continuation of precast concrete panel installation at the retaining wall south of Illinois Route 22 and the excavation for a retaining wall at Buffalo Creek.  Storm sewer crews continue to work north of Boschome Drive and south of Illinois Route 22.  This work will be ongoing for the next few weeks.  Please note storm sewer crossing under Boschome Drive is anticipated to be installed mid-week.  Traffic will be allowed to access Boschome Drive at all times but it may be reduced to one lane during working hours.  Please watch for flaggers.

Please check the Photos tab for more in-depth information regarding the project.