Work on the retaining wall at Buffalo Creek continued despite the wet conditions. In addition to setting precast concrete wall panels, a concrete wall panel was poured in place to allow the 78” concrete pipe culvert to pass through the wall. At the retaining wall south of Illinois Route 22, reinforcing steel was installed and concrete poured for the anchor slab sitting atop the wall. Storm sewer work continued south of West Cuba Road and north of Pine Lake Circle. Removal of the steel sheets for the temporary retaining wall north of Greenwood Drive was completed. Efforts were made to dry the clay embankment following several rain events. Removal of the existing pavement continued south of West Cuba Road. This week, storm sewer work will continue south of West Cuba Road. Earthwork will continue at various locations pending weather. Work will continue at the retaining wall at Buffalo Creek and work will begin on the retaining wall north of East Cuba Road.

Please check the Photos tab for more in-depth information regarding the project.