Update – 9/17/19

Concrete curb and gutter for the first stage of work was completed early last week. 

Asphalt paving started last week on the future northbound Quentin Road lanes.  The asphalt will be placed in four separate passes (or lifts) due to different material specifications and to achieve compaction requirements.  Three of the four lifts will be placed now, with the final lift being placed at the end of the project.  Work on the first three lifts will continue through the end of this week.  As a reminder, this will require multiple trucks pulling into and out of the work zone.  Please use caution and watch for flaggers and workers.

A joint sealer will be placed on the joint of two pavement passes.  The sealer will help extend the life of the pavement by limiting water infiltration into pavement joints.

A new traffic pattern is anticipated for the week of September 23rd.  Northbound traffic will be shifted east through the project limits.  This is necessary to construct areas of the future medians and temporary pavement.  This lane configuration will be in place until approximately the end of October when southbound lanes will be shifted east.   

Other work anticipated for this week includes topsoil placement, placing aggregate for the future shared use path on the east side of Quentin Road, and underground conduit installation for the traffic signals at East and West Cuba Roads.

Please check the Photos tab for more in-depth information regarding the project.