Update – 10/28/19

Work in the median of Quentin Road continued last week throughout the project limits.  Similar to the previous week, pavement removal was followed by extending the storm sewer crossings, grading, and installing temporary asphalt pavement.  Paving in the medians is expected to continue through the end of this week.  Eastbound traffic on East Cuba Road was shifted south.  This allowed the old pavement on the north side of the road to be removed and excavated, along with aggregate placed for the new road bed.  Concrete curb was poured along the north edge as the last step before pavement is placed.  Temporary paving in the median of Quentin Road and on West Cuba Road will continue this week.  Permanent pavement is anticipated this week on the north side of East Cuba Road. The current lane configuration is expected to be in place until the beginning of November.  When paving is completed in the center of Quentin Road, the southbound lanes will be shifted east so the west side of the road can be constructed.  Pavement marking for the next stage of construction may begin this week.  This lane configuration will be in place through the winter. Please check the Photos tab Read More

Update – 10/21/19

Work in the median of Quentin Road continued last week throughout the project limits.  Pavement removal was followed by extending the storm sewer crossings, grading, and then asphalt pavement.  The pavement installed at the north and south project limits is permanent; the areas in between will be temporary and is needed to maintain traffic while the west half is constructed.  Paving is expected to continue through the end of the week.  The shared use path was also paved last week.  The gaps at the intersections will be constructed in concrete with ADA warning tiles at the curbs.  This work is expected to be complete near the end of the week.   Work will continue in the median this week to prepare for asphalt pavement.  In addition, westbound traffic on East Cuba Road is expected to be shifted south so the north half of the road can be constructed.    The current lane configuration is expected to be in place until the beginning of November.  When paving is completed in the center of Quentin Road, the southbound lanes will be shifted east so the west side of the road can be constructed.  This lane configuration will be in place through the Read More

Update – 10/14/19

Removal of the existing pavement in the middle of Quentin Road continued last week.  The material that is being removed will be processed and recycled for reuse as the subgrade below the new pavement.  This operation will continue through the end of the week.  Storm sewer crossings were extended through the median.  The crossings will direct water collected in the curb of the future southbound lanes eastward.  Storm sewer work will occur sporadically over the next couple of weeks as pavement removal and working space becomes available. Asphalt paving is expected to resume this week.  Areas to be paved include the far north and south job limits and the median on East Cuba Road.  The shared use path is also anticipated to be paved.  Other work expected this week is earth excavation, grading, and aggregate installation in the median. The current lane configuration is expected to be in place until the beginning of November.  When paving is completed in the center of Quentin Road, the southbound lanes will be shifted east so the west side of the road can be constructed.  This lane configuration will be in place through the winter. Please check the Photos tab for more in-depth information Read More

Update – 10/07/19

Last week the next stage of construction started as northbound traffic was shifted east into a new lane configuration on Monday.  Removal of the existing pavement in the middle of Quentin Road, which started last Tuesday, will continue over the next couple of weeks.  This will be followed by extending storm sewer pipe crossings, aggregate placement, and asphalt paving.  Contractors also continued installing fencing at the retaining walls and foundations and conduits for future traffic signals.  Work is expected to finish this week on the east side of Quentin Road. Work anticipated over the next couple of weeks includes paving the shared use path on the east side of Quentin Road and installing permanent landscaping.  The current lane configuration is expected to be in place until the beginning of November.  When paving is completed in the center of Quentin Road, the southbound lanes will be shifted east so the west side of the road can be constructed.  This lane configuration will be in place through the winter. Please check the Photos tab for more in-depth information regarding the project.