Update – 11/11/19

On Tuesday last week, pavement markings and new signage were installed to shift southbound Quentin Road traffic eastward.  This lane configuration will be in place throughout the winter.  Following the shift in traffic, topsoil stripping on the west side of Quentin Road started on Wednesday and continued through the end of the week.  Also, last week, the topsoil that was stripped was re-spread on the east side of Quentin Road and final graded.  Installation of temporary aggregate shoulders also occurred throughout the project limits.  

Work anticipated this week includes continuing topsoil striping, along with placement and final grading on the east side of Quentin Road.  Areas which have been topsoiled are scheduled to be landscaped this week as well.

Nicor gas crews returned to the site to begin removal of the 18” gas line that was retired last May.  Removal started north of West Cuba Road and will continue northward to Illinois Route 22.  This work is expected to continue through the end of the year.

Please check the Photos tab for more in-depth information regarding the project.