Update – 01/13/2020

Work on the project site resumed last week.  Crews continued installing the new retaining wall on the west side of Quentin Road across from Boschome Drive.  Excavation for the wall, panel installation, and backfilling at this location will continue over the next few weeks.  If weather conditions allow, storm sewer installation may begin north of West Cuba Road.

Nicor gas crews resumed work this week on the removal of the 18” gas line that was retired last May.  These removal efforts will continue through the end of January.

Please check the Photos tab for more in-depth information regarding the project.