Update – 02/03/2020

Retaining wall installation continues on the west side of Quentin Road across from Boschome Drive.  Crews are expected to reach the south end of the wall by the end of the week and then will begin working northward.  This wall is expected to take several more weeks to complete. Preliminary work on the noise abatement wall near the Quentin Road and West Cuba Road intersection is anticipated to begin the week of February 17th.  Please keep in mind all construction activities, particularly during winter months, are dependent on weather and crew availability.

Nicor gas crews completed removal of the removal of the 18” gas line that was retired last May.  Final restoration work disturbed by these crews will be completed in the spring.