Update – 07/15/2020

Construction started on a retaining wall north of Lea Lane.  A truck was supplied by ComEd to support a utility pole while the wall is being constructed due to excavations near the base of the pole.  Construction of this wall is anticipated to be complete this week.   Hot-mix asphalt was placed on the north half of West Cuba Road and at Pheasant Ridge Drive.   Paving is completed for this stage of work.  The next area of permanent pavement will be in the medians.   Noise abatement wall panel installation as well as drilling and pouring foundations for the noise abatement walls resumed over the last two weeks.  Columns were placed on the poured foundations.  Additional noise abatement wall panels are expected to be installed this week.  One column north of Pheasant Ridge Drive and several columns south of Bristol Trail Road will be completed at a later date due to utility conflicts.   Other project work over the last couple of weeks included installing traffic signal foundations at the West Cuba Road and East Cuba Road intersections.  Work anticipated over the next couple of weeks includes grading for sidewalk on the west side of Quentin Road and pulling traffic Read More