Update – 04/21/2020

Noise abatement wall construction continues.  The remaining precast columns and panels have been installed between West Cuba Road and Pheasant Ridge Drive.  Noise abatement wall column installation will begin this week north of Pheasant Ridge Drive.   Work continues at multiple retaining walls throughout the project limits.  The parapet for the wall north of Pine Lake Circle is now complete since the last portion was poured on Friday, April 17th.  Work on the retaining wall north of East Cuba Road is ongoing and is expected to continue for the next several weeks.   Permanent landscaping on the east side of Quentin Road continues.  Sod is being placed between the curb and shared use path.  West of the shared use path, crews will place seed and erosion control blanket.  Landscaping on the east side of Quentin Road will be complete near the end of this week.   Other project work over the last couple of weeks includes removal of the old southbound Quentin Road lanes and portions of West Cuba Road.  Crews will removed existing storm sewer, curb and gutter and driveways within the project limits.  In the next couple of weeks, installation of storm sewer and placement of aggregate for Read More

Update – 6/18/19

This past week earth excavation and roadway embankment placement continued.  The embankment placement included filling the deep excavations at the ground improvement areas between East and West Cuba Roads and north of Greenwood Drive.  Work this past week also included the continuation of precast concrete panel installation at the retaining wall south of Illinois Route 22 and the excavation for a retaining wall at Buffalo Creek.  Storm sewer crews continue to work north of Boschome Drive and south of Illinois Route 22.  This work will be ongoing for the next few weeks.  Please note storm sewer crossing under Boschome Drive is anticipated to be installed mid-week.  Traffic will be allowed to access Boschome Drive at all times but it may be reduced to one lane during working hours.  Please watch for flaggers. Please check the Photos tab for more in-depth information regarding the project.

Update – 3/18/2019

Work continued preparing the two ground improvement areas on the east side of Quentin Road between East and West Cuba Roads.  Temporary pipe will be installed this week to bypass the existing sanitary sewer around the ground improvement areas.  Steel H-piles will be installed this week as construction begins on a retaining wall south of Boschome Drive.  Sheet piles will also be installed for a temporary soil retention system north of Greenwood Drive. Nicor Gas crews continued work on the 4” distribution system in the area of Lea Lane, Greenwood Drive and Bristol Trail.  Work on the distribution system is anticipated to be complete the week of March 25th.    AT&T crews continue pulling new cables in conduits and splicing aerial cables at various locations throughout the project.  Splicing on both the fiber optic and copper cables is expected to be complete in April.  The old cables are scheduled to be taken out of service April 18th through April 22nd.  Please check the Photos tab for more in-depth information regarding the project.