Sand backfill is placed and formwork is installed for the retaining wall at Buffalo Creek north of East Cuba Road. Upon completion of the formwork, reinforcing steel will be installed and concrete poured. An extension of the noise abatement wall will be constructed on top of this retaining wall. (5/4/2020)